At Greater Pacific we understand that speed, momentum on-time delivery and a worry-free experience are key to your success and peace of mind. With this in regard, we delivered 33,000 custom minion sets of 4 figurines within 30 days of PO! Here is a snapshot of this impressive timeline:
04/15 Received screen shots/images from client to match
04/20 Manufacturer completed clay molds for client approval
04/23 Client issues rush PO
04/23 Tooling starts for each character
04/24 E-Images are provided to confirm match of character PMS colors
04/27 Box art/template provided to manufacturer
04/28 e-proofs for boxes provided
04/29 Final approvals given on all project aspects
04/30 Full production begins on all project aspects
05/05 Initial (first-off) minion set samples show production quality
05/19 Greater Pacific conducts QC inspection and certifies "PASS" on production
05/21 Project shipped complete from China